Skip Navigation
Expand
Changing the Status for a Task changes the Percent Complete
Answer ID 10812   |   Last Review Date 02/25/2020

Why does changing the Status for a Task change the Percent Complete?

Environment:

Task Workspaces
Oracle B2C Service

Cause:

There is a tie between two fields, Status and Percent Complete in the task workspace. 

  • A Percent Complete setting of 0 will trigger a Status of "Not Started"
  • A Percent Complete from 1-99 will trigger a Status of "In Progress"
  • A Percent Complete of 100 will trigger a Status of "Completed"
  • A change in Status from "Complete" or "Deferred" to "Waiting" will set the percent completed field to 0
  • A change in Status from "In Progress" to either "Waiting" or "Deferred" with a percent less than 100 will retain the current Percent Complete value.


For more information on Tasks, refer to Adding and Editing tasks.

Notify Me
The page will refresh upon submission. Any pending input will be lost.