Skip Navigation
Expand
My preferred cutover date is not available
Answer ID 10933   |   Last Review Date 12/13/2023

Why am I unable to select certain dates or times while scheduling an Oracle B2C Service update cutover?

Environment:

Oracle B2C Service, Site Update, All versions

Resolution:

Cloud Configuration Assistant only displays available dates and times. A customer’s preferred cutover date and time may not be visible in Configuration Assistant for the following reasons:

  1. Another customer hosted in the same data center scheduled their cutover for that date and time
  2. Regular weekend maintenance or long-term maintenance of Oracle data centers is scheduled
  3. Oracle Corporation blackout periods coinciding with company holidays

Cutover Blackout Period (all in US Pacific time PST/PDT):

  • All day 1st & 3rd Friday 00:00 - 23:59, 2nd & 4th Friday 12:00 - 23:59 plus the 1st and 3rd Saturdays (exception applies) 00:00  - 12:59, except the 5th Friday of the month (e.g. no maintenance on 31 January 2020)

2023

  • 1 January 00:00 - 1 January 23:59
  • 27 May 00:00 - 29 May 23:59
  • 1 July 00:00 - 4 July 23:59
  • 2 September 00:00 - 4 September 23:59
  • 23 November 00:00 - 27 November 23:59
  • 23 December 00:00 - 31 December 23:59
2024
  • 1 January 00:00 - 1 January 23:59
  • 25 May 00:00 - 27 May 23:59
  • 4 July 00:00 - 7 July 23:59
  • 31 August 00:00 - 2 September 23:59
  • 28 November 00:00 - 1 December 23:59
  • 25 December 00:00 - 31 December 23:59
2025
  • 1 January 00:00 - 1 January 23:59
 

Notes:

  • The above schedules may change without prior notice
  • Oracle may schedule additional emergency data center maintenance without prior notice

To receive notification when this schedule is updated, select the Notify Me option from the right on this page.